Sl. No. Name of majorwork Contractingagency Value of work (Rs. in(crores) Amount utilized during the year _____ Likely time of Completion Target date of completion
Water supply Improvements
1 UIDSSMT:Laying of Water Supply distribution pipe lines and Construction of OHSRs M/s. Premier Plastic Industries , Hyderabad 2.316 1.8799 31.03.2012
M/s. Kaveri Poly, Hyd
Sewerage M/s. Ramkey Infrastructe 45.5929 27.7197
improvements
Major Road works
1 IHSDP:Laying of CC Roads, and  Community Utility Centers in the town M/s.ARR  Projects Ltd 17.2221 1308.18 19.01.2009 31.03.2012
Major drain works
2 13th Finance Commission ( Rs. In lakhs ) 2012-13
Construction of 800K Capacity RCC OHSR M/s Shobha constructions , Hyderabad 129.00
(121.00 13th FC + 8.00 Mpl.Genera funds )
30.06.2014 30.06.2014
Reimbursement towards construction of 800KL OHSR Sanctioned under F.Y.2011-12 Total cost of 800KL OHSR is 121.00 Lakhs out of which Rs.91.61 Lakhs was sanctioned under F.Y.2011-12 balance amount of Rs.29.39 lakhs is proposed under F.Y.2012-13 M/ Kaveri Polymers , Hyderabad 29.39 31.12.2013 31.12.2013
Extension of Street Lighting with new electrical poles with fixures in town –I 9.25 13.43  Completed  Completed
Extension of Street Lighting with  new electrical poles with fixures in town -II 7.69 Completed Completed
(167.33 + 8.00 Mplfunds) =
175.33
Service Level Benchmark 4.95
Double Entry Accrual Based Accounting System 7.68
Total Amount for 2012-13   (179.96+8.00 Mpl.funds) =
187.96